DendroRemediation - HOME - new Window3 Planning
Home Engl ] www.dendroremediation.de/index.html ] Start page ] Address ] Summary ] 1 Problem ] 2 Project conditions ] [ 3 Planning ] 4 Initial scientific basis ] 5 Co-operation ] 6 Results -> ] 7 Usability ] 8 Progress of others ] 9 Publications ] 10 Literature ] All figure and table links ] Tables ] Formulas and TNT degradation ] Photos ] Bibliography ] External PhytoRemediation Links ]


 

previous pagePrevious page  

next pageNext page

3 Planung & Ablauf

Project directory according to Nr.3.2 BNBest-BMBF98 <http://www.fz-juelich.de/ptj/datapool/page/490/Schlussbericht.rtf>

3 Planning and realisation of the project

Work and schedule

The individual phases and activities of the project are detailed in fig. 1
The graphical project summary is shown in fig. 3.

Outdoor experiments were conducted using a plot design with 72 lysimeter pots (30 kg dry soil each), which allowed monitoring of leachate water  and thus opened mass balance possibilities.

The original schedule was extended on dynamical dendrotolerance/dendrotoxicity investigations with quantifiable TNT input using various glass fibre wick application systems.

Financial program

The central expenditures were near below  the allowance answer of 810,400 DM. Higher expenditures for staff (on the average 9 %) were compensated by savings within the other ranges.


last updated: 18.02.04 19:41 by Bernd Schoenmuth  previous page   next page     Web date: June 2002